Mitel Phone Installers on Campus Today

Today (10/29) Mitel technicians started installing the new phones in buildings scheduled to migrate to the new phone system tomorrow.  They are caring ID cards if there are questions of who they are.  It will take only a few moments per office to install a phone and your flexibility is appreciated.  The complete installation scheduled is as follows.  

10/29

Buildings Scheduled

  • 454 House
  • Quigley Hall
  • Arter Hall
  • Doane Hall of Chemistry
  • Steffee Hall of Life Sciences

10/30

Buildings Scheduled

  • Tippie Alumni Center
  • Murray Hall
  • Montgomery Gym
  • Alden Hall
  • Vukovich Center
  • Carr Hall 

Set Up VoiceMail
Once the phone is on your desk, you should set up your voicemail by pressing the voicemail button  on your phone entering the default pin code, and following the tutorial. 

10/31

Buildings Scheduled

  • Newton Observatory
  • Schultz Hal
  • Brooks Hall
  • Carnegie Hall
  • Ruter Hall
  • Odd Fellows Hall

11/1

Buildings Scheduled

  • Campus Center
  • Arnold Hall
  • Doane Hall of Art
  • Robertson Athletic Fields
  • Wise Center  

Should the technicians need extra time, they will use Friday, November 2 to complete their work.  Please contact James Fadden by email should you have questions about the installations or how the rest of campus will migrate to the new phone system.