Phase 1
Completed January 2018
- Original structural evaluation (completed June 2014)
- Original Mechanical, Electrical, Plumbing (MEP) evaluation (completed December 2015)
- Comprehensive evaluation – combining and updating Structural and MEP evaluations, proposed floorplans and comprehensive budget estimate (completed January 2018)
Phase 2
January – July 2018
- Selection of architectural firm (selected March 28, 2018)
- Board of Trustee approval of Bentley renovation project and financing plan (approved May 12, 2018)
- Selection of engineering firm (selected June 28, 2018)
- Selection of general contractor (selected July 9, 2018)
- Preliminary investigations
- Pre-design discussions
Phase 3
August 2018 – May 2019
- Development of design and detailed cost estimates
- Relocation of Bentley occupants
Phase 4
April – May 2019
- Subcontract bidding
- Mobilization
Phase 5
June 2019 – August 2020
- Construction
- Fit-out
- Commissioning
Phase 6
August 2020
- Occupancy
Phase 7
October 2020
- Rededication Ceremony