Timeline

Phase 1

Completed January 2018

  • Original structural evaluation (completed June 2014)
  • Original Mechanical, Electrical, Plumbing (MEP) evaluation (completed December 2015)
  • Comprehensive evaluation – combining and updating Structural and MEP evaluations, proposed floorplans and comprehensive budget estimate (completed January 2018)

Phase 2

January – July 2018

  • Selection of architectural firm (selected March 28, 2018)
  • Board of Trustee approval of Bentley renovation project and financing plan (approved May 12, 2018)
  • Selection of engineering firm (selected June 28, 2018)
  • Selection of general contractor (selected July 9, 2018)
  • Preliminary investigations
  • Pre-design discussions

Phase 3

August 2018 – May 2019

  • Development of design and detailed cost estimates
  • Relocation of Bentley occupants

Phase 4

April – May 2019

  • Subcontract bidding
  • Mobilization

Phase 5

June 2019 – August 2020

  • Construction
  • Fit-out
  • Commissioning

Phase 6

August 2020

  • Occupancy

Phase 7

October 2020

  • Rededication Ceremony